The Macbeth Hut site, September 23. Photo: Alex Clapin
The foundation is finished and wrapped up for winter. Here’s how the summer went, and where things stand with the fundraising.
$4.6M raised of $6M
We need $1.4M more to finish the hut. If all goes to plan, the first ski touring parties arrive in winter 2028/2029.
What we’re building
The finished hut, as designed. Rendering: MGA | Michael Green Architecture
The Macbeth Hut is the second of three huts planned along the Spearhead Traverse, the 34 km ski route between Whistler and Blackcomb. It sits near the midpoint, on the shoulder of Mt. Macbeth, and will sleep 24.
MGA | Michael Green Architecture designed it as a classic A‑frame, shaped around the sun, wind and views on the site. The structure is low-carbon wood, and the Passive House standard wall panels are prefabricated in the valley, so less of the build has to happen on the mountain.
How the summer went
When the crew flew in at the end of July, the site was rock and not much else. TM Builders spent the next 10 weeks digging out the footprint and building the foundation, and every load of material came up on the end of a helicopter long-line.
By late September it was done. The crew wrapped it in a permanent weather seal, packed up camp and flew out. It’ll spend the winter under the snow.
Another load on the long-line
The TM Builders crew. Photos: Alex Clapin
Huge thanks to TM Builders, and to Howler Contracting, who ran the camp all season.
MGA’s drawings for the hut, out on site this summer. Photo: Alex Clapin
Meanwhile, in Pemberton
While the site sits under snow, the hut itself is taking shape in the valley. At BC Passive House in Pemberton, the floor package and much of the A‑frame structure are being prefabricated in the shop, so when we go back up in May 2027, a lot of the hut will be ready to put together.
Help us finish it
This first season was paid for by a small group of lead donors, and we’re so grateful to them. The rest is up to all of us. We have about $1.4 million left to raise, plus a buffer for rising construction costs, to get the hut built over the next two seasons.
If you’re planning a year-end gift, we’d love for it to go to Macbeth. You can also sponsor a specific piece of the hut and have your name on it.
Spearhead Huts Society is a registered charity (#78075 3299). Gifts made by December 31 receive a 2026 tax receipt. Camp photo: Alex Clapin